Hello Guru's,
I have a scenario of capital proejcts. Were I create Assets with the help of Investment profile at the top(1st level) WBS element. Now my requirment is the cost of the second level WBS should be rolled upto top level WBS element. To do this I have to manually create settlement rule for all second level WBS to settle at top level. I have to create this rule automatically throught CBJ2 tcode.
As per SAP Note 211324 I have Implemented the modification. Now I have Insert value '5' with short text 'Superior WBS element'. Also have assign the strategy to Acct. Assign element. This strategy is also assigned to settlement profile. Also have assigned this settleemnt profile to project profile.
Now, when i run CJB2 tcode for my project the system issues me an error :-
Error(s) during creation of settlement rule
Message no. ORB509
Diagnosis
Errors occurred during the check on settlement receivers.
System Response
Processing stopped.
Procedure
Check whether the:
Specific receiver Account assignment e actually exists
Settlement profile ZPI03 permits account assignment to the specified receiver
Please throw some light on this error
Regards,
Tushar
make sure that all WBS elements have account assignment operati indicator ticked
also check if the settlementn profile ZP1093 allows settlement to WBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.