Unit costing...for quotation creation

Former Member
0 Kudos

I am using ECP for creating quotation through project.(dip is used)

i also want to check the Unit costing, is it so possible to creat quotation form unit costing? if so wht are the setting i have to change in my DIP profile?

pls do the needful

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks

virendra_pal
Active Contributor
0 Kudos

in dip profile for the source costs use plan costs v0 and not ECP vx

with unit costing I am not sure if you can do sales procing from CJ20N - this means that may will need to use a sales inquiry with dip profile to trigger DP91- check it out