on 03-19-2009 11:10 AM
Hi experts,
We are releasing the project in CJ02, all the WBSE and Project Definition status are getting released and set to 'REL' but the networks and activities are not getting released. It is still in CRTD status. Is this standard behaviour or we are doing something wrong?
CJ02 is a specifi transaction which does not affect networks
if you need network/ activity to be released then use CN22
otherwise you can use CJ20N where you can do evrything in one hit