Dear Gurus,
Given below is a scenario
An activity has a duration of 10 days and work of 100 m3. start date: 1st Apr & finish date is 10th Apr. And activity is linearly distributed.On 5th Apr, if confirmation is 40 m3 of work completion instead of a planned completion of 50 m3, then on re-scheduling, system should propose a new forecast finish date for the activity, keeping the planned dates same.
pls suggest the configuration/customization required.
Regards,
VDS
Edited by: Rupesh Prajapati on Mar 18, 2009 9:27 PM
system will update only planned dates
what you need to do is copy these planned dates to the forecast dates - there is a std function which you can use via the menu path in the planing board
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
while scheduling the activities the system will consider the scheduling type and the relationship maintain in between the activities and if you run the forecast dates for the activities the system will call calculate and propose the dates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.