cost in project

former_member711289
Participant
0 Kudos

hi every one whenever i m creating an activity and giving it some hour. it is working properly but the problem is like whenever i m going to see plan/actual cost that rate is different from watever i have given in kp26. one more interesting thing is when i m going to project planning board and if i m running a report there for cost that cost is coming as per kp26. i m not getting y its coming different in plan/actual in builder . thanx in advance....

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please make sure you have activated Plan Cost Calculation (Determine Plan Costs from the drop down) in your network parameters configuration step - txn OPUV.