on 03-18-2009 10:49 AM
Hi there
Is there anybody that can shed some light for me on a problem I have.
I am looking for a screen input area or tab strip on a change document where I can enter actual hours worked on a change.
I have gone through the screen customising to add such a tabstrip: (CRMV_SSC - Mntce: Scrn Cntrl Data - CRM Trans.)
I only have the following tabstrips available on my transction
SRVO_HD_OBJECT 7235
SRVO_HD_PARTNER 7180
SRVO_HD_TERMINE 7220
SRVO_HD_ORG 7190
SRVO_HD_ACTION 7140
SERVICE_OV_STATUS 7185
SERVICE_CMDOC_HDR 6000
CRM_CUSTOMER_H 7196
SOCM_CNTX 100
SERVICE_ADMINST 422
I need to add another one where I can enter actual time spend on a change: Is there a standard screen for such a thing or will I have to develop such a tabscreen.
JB
Johan,
I am not sure if you can do that using tabstrip ..or modify standard using CRMV_SSC
But to meet you requirement it is easy to do with EEWB functionality for CRM Transactions
You can create a lot of fields in the lower portion of screen of crmd_order or the ticket.Thus you can create an effort field with EEWB or easy enhancement workbench easily.Please check these
links
http://help.sap.com/saphelp_crm50/helpdata/en/20/a4ffee7e0fcc4ebb7e5466d3903d38/frameset.htm
http://help.sap.com/saphelp_nw04/helpdata/en/80/4349e31fb911d6b1d200508b5d5211/frameset.htm
Regards
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
81 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
6 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.