Hi All
we have a peculiar problem with life cycle planning , we use SCM 4.1 Version and since last 2 months our Phase in and Phase out, assigments we assigned in life cycle planning are not getting applied correctly. I checked all the setting and also spool list from the background job. Phase outs which are seen in setting are not getting applied in the job during material level forecast.
Can someone suggest what else to look at.
Thanks
KV
Hi
Please check if the Life cycle planning is selected in Forecast profile, check if al your from and to dates are correct. Also check OSS note: 1222953. We applied this when we had a similiar issue and ot worked for us.