on 03-17-2009 3:16 PM
Hi Gurus,
I am investigating between CJ20N anc CJ02. I like to know which one is better for asset accounting area. Please provide your thought.
Thanks,
Song
CJ02 you can only see WBS elements and Project definition but not networks
CJ02 is an older transaction and the navigation is a bit different
I would use CJ20N as it has more functionality.
However if you do not have networks (which should be true for asset project as a best practice) then there you do have to choose
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
that is usually the problem!!
in my current implmentation I am having the same probelm to convince my users to use CJ20N, but they are so stuck with CJ02 that it is a huge change for them, so I am testing waters with a few superusers with CJ20N and rest continue as before
As a consultant I would try to show both sides of the coin and give the recommended option as you think - then leave it to your associates to decide - at least later they cannot say you didn't tell them !!
The only thing I would state is that in CJ20N you can
the system remembers the last 5 project numbers
if there are networks involved then you can do everything in one go
you can access planning board from CJ20N
adding and extending project structures is easy with the template area