Update activity dates

Former Member
0 Kudos

Hello all, I need to update the real dates in an activity from a network.

I am using BAPI BAPI_BUS2002_ACT_CHANGE_MULTI, but I don't find any fields related with real dates, or something like actual dates.

Could someone give me a hand on this, please?

Thanks in advance!

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jorge,

You can update real data, using standard notification function, related to network elements from PEP element.

On "data tab", there are all data you can use, included real data (PRTE-ISTRT, PRTE-IENDE, PRTE-VISTR, PRTE-VIEND).

Hope this helps,