HI EXPERTS
at the time of changing project when i wanted to do work force planning or click on work force planning to assign persons to the activity an error comes like this
"No requirements were found for the selection criteria"
can any body suggest me any solution
thanx in advance
subhro
answers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Subu,
U need to check capacity reqmt in network. Than in activity u need to put work center, no of hrs on that activity. than only u shoudl go for personnel assignment in activity.
Regards
Abhishek Sinha
Idhasoft
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In CJ20N, select the network header and put the tick on CAPACITY REQTs
to make it as default in Customization , put the tick in releavant network profile.
Additionally check the control key .. DET. CAP. REQ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
open project with nertworks in planning board - txn CJ2B
select all
menu path edit -> functions -> activate capacities
select all schedule
save and exit from planning board and project
now go to CMP2
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
check whether you have maintain the planned hours for the work force planning.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.