cancel
Showing results for 
Search instead for 
Did you mean: 

work force planning

Former Member
0 Kudos

HI EXPERTS

at the time of changing project when i wanted to do work force planning or click on work force planning to assign persons to the activity an error comes like this

"No requirements were found for the selection criteria"

can any body suggest me any solution

thanx in advance

subhro

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

answers

former_member711289
Participant
0 Kudos

Hi Subu,

U need to check capacity reqmt in network. Than in activity u need to put work center, no of hrs on that activity. than only u shoudl go for personnel assignment in activity.

Regards

Abhishek Sinha

Idhasoft

Former Member
0 Kudos

Hi,

In CJ20N, select the network header and put the tick on CAPACITY REQTs

to make it as default in Customization , put the tick in releavant network profile.

Additionally check the control key .. DET. CAP. REQ

virendra_pal
Active Contributor
0 Kudos

open project with nertworks in planning board - txn CJ2B

select all

menu path edit -> functions -> activate capacities

select all schedule

save and exit from planning board and project

now go to CMP2

Former Member
0 Kudos

hi

check whether you have maintain the planned hours for the work force planning.