No costs were calculated for the activity

Former Member
0 Kudos

Dear Guru's,

I was trying to calculating planned cost in project systems. There I am getting "No costs were calculated for the activity" for few activities. I maintained activity price in KP26 transaction also. Can any one please explain how system will calculate planned cost and actual cost.

Regards

dnr

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi,

Please go through the below thread you will get all your answer.

Prashant

Former Member
0 Kudos

Hi,

Please check '' Network type parameters'' ( OPUV ) for Plan Cost calculation.

Regards,