Hello All,

The requirement is to configure a BOM, with Main item and 2 components/Sub Items

Pricing on the Main Item Only, so i guess that would be ERLA Item Category Group, or if something customized is needed.

1st Component would be externally Procured and Drop Ship to Customer , so i guess the Item Category should be TAS, because it needs to create and PR automatically.

2nd Component is actually a Assembly Item, with BOM attached to it, Needs to Explode in Production Order, run MRP , Procure the Material if required for Assembly , do the goods receipt, Start the Production/Assembly and Ship out the Assembly to the Customer.

The Billing for the Above Main Items Needs to be Milestone Billing.

Your Inputs on this would be appreciated.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear fnd,

As per my Understanding on u r Thread..

X is main material with Components(x1+x2)...maitian milestone for this line itemmm

1st milestone is -Advance amount

2nd Milestone is -Againest to Dispatch in Billing plan tab in Sales order.

1st milestone W.r.to Sales order

2nd milestone wrto Delivery.

Revert us back if u need more clarity

Regards

raj