on 03-12-2009 3:03 PM
Dear friends,
I need your help in the following issue
Ours is simple Classic scenario
We have created Shopping cart it got approved and got created. When we tried to do Goods confirmation , the confirmation number got created but PO in R3 had not created
We did the following analysis
1.The status of goods confirmation is still in " Awaiting Approval"
2. We checked for IDOC failures both in back end (R/3) and SRM GU1. there is no failure
3. We checked for any entry in table "BBP_DOCUMENT_TAB" and could not see any entry
4. Checked for Application monitoring for any Goods receipt related errors for this PO. But could not get any details
5. Checked the goods confirmation for details like PO excess qty , posting date etc.., but seems to be OK
Could some one help me to fix the issue?
Thanks
Deva
Confirmation needs to be approved before it posts an IDOC and GR in R/3. It is the issue with workflow. Make sure that workflow is configured.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes confirmation in SRM system have to approve first. Once the approval process over GR will be
created in backend system.
Check the Purchase order status of the SC.
if the problem occurs please check in RZ20 for Confirmation errors also check inbound and outbound
idoc's of confirmaitons in SRM and ECC
HI Friends ,
I am very sorry .
The issue is Goods confirmation got created but GR not created in R/3.
Sorry for the inconvenience
Please help
Deva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.