do i can do cost planing for WBS element at ontime more than one WBS elemen

Former Member
0 Kudos

hi experts,

can any one tell me can i give cost planing at a time more than one WBS element,

now i am using CJ40 for giving cost planing

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Use TC CJ9ECP this transaction edit easy cost planning for specified WBS.

Former Member
0 Kudos

hi, virendra,

in CJR2 i can able to give From WBS element to To WBS element in this i am giving from and to then i entered some amount to frist WBS element, then i pressed to next combination icon but its not coming how can i give selected WBS elements

thx

Former Member
0 Kudos

just enter into CJ40 transaction,

u can see the editable fields to enter value against all planning WBS elements (whose planning element indicator is ticked).

Means..planning allowed for multiple wbs at a time.

ashis

virendra_pal
Active Contributor
0 Kudos

in structural planning CJ40 you can use only for only one project

in CJR2 you can use cosrt element planning for a list of WBS - this an be also be integrated with flexible upload to transfer data froma excel template to SAP PS for planning