on 03-12-2009 2:19 PM
hi experts,
can any one tell me can i give cost planing at a time more than one WBS element,
now i am using CJ40 for giving cost planing
Use TC CJ9ECP this transaction edit easy cost planning for specified WBS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi, virendra,
in CJR2 i can able to give From WBS element to To WBS element in this i am giving from and to then i entered some amount to frist WBS element, then i pressed to next combination icon but its not coming how can i give selected WBS elements
thx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
just enter into CJ40 transaction,
u can see the editable fields to enter value against all planning WBS elements (whose planning element indicator is ticked).
Means..planning allowed for multiple wbs at a time.
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
in structural planning CJ40 you can use only for only one project
in CJR2 you can use cosrt element planning for a list of WBS - this an be also be integrated with flexible upload to transfer data froma excel template to SAP PS for planning
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.