on 03-12-2009 8:50 AM
Dear all,
I have following requirement in Calibration of test equipment,
We are attaching Test Equipment as PRT in Inspection plan. when calibartion order is due for this equpment it shoud block usage of equipment, means user should not be allowed to do Result recording if Equipment used is due for calibartion.
Thanx & Regards,
Harish.
Hi harish..
this is not not STD SAP functionality.but needs some development or user exit during UD.
Logic can be ......
during UD it should go and check STEUF(control key for PRT) & SFHNR(PRT) fileds
If this matches with NPLDA(next plan date) in MPOS table then UD should not be allowed.
If cofirmation(LRMDT -MPOS) done for PRT then UD can be taken
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
do you know the user exit name.?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.