Blocking of result recording if equipment due for calibration.

Former Member
0 Kudos

Dear all,

I have following requirement in Calibration of test equipment,

We are attaching Test Equipment as PRT in Inspection plan. when calibartion order is due for this equpment it shoud block usage of equipment, means user should not be allowed to do Result recording if Equipment used is due for calibartion.

Thanx & Regards,

Harish.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi harish..

this is not not STD SAP functionality.but needs some development or user exit during UD.

Logic can be ......

during UD it should go and check STEUF(control key for PRT) & SFHNR(PRT) fileds

If this matches with NPLDA(next plan date) in MPOS table then UD should not be allowed.

If cofirmation(LRMDT -MPOS) done for PRT then UD can be taken

Answers (1)

Answers (1)

Former Member
0 Kudos

do you know the user exit name.?

Former Member
0 Kudos

Hi

try using QEVA0010 UD: Usage decision check