How to view the results of progress analysis

Former Member
0 Kudos

Dear Experts,

I executed progress analysis for my project analysis in CNE1 for my project.

After execution, PA has been completed for two WBS elements. But iam not able to see any POC values or costs.

Where should I check and confirm that Progress analysis has been carried out successfully.

Pls suggest.

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Run the report CNE5 to see the values

Answers (2)

Answers (2)

Former Member
0 Kudos

u can see the same in report "S_alr_87015124" n "S_alr_87015125"..

ashis

Former Member
0 Kudos

Hi,

Run the transactio CNE5 for the project progress analysis ,you will get the following reports.

The standard reports offer various values we can use to assess the progress of our project. The following fields are defined in the standard progress analysis reports:

- Planned POC in percent

- Actual POC in percent

- Budget Cost of Work Schedule, BCWS

- Budget Cost of Work Performed, BCWP

- Cost variance (CV)

- Schedule variance (SV)

- Value index (CPI)

- Estimated costs at completion (EAC)

Regards,

Raj

Former Member
0 Kudos

Hi Raj, Ahmed and ashis,

Thank you for your replies. Actually, i was not able to view the values in the report.

Now it has been resolved.