cancel
Showing results for 
Search instead for 
Did you mean: 

assign activity to wbs

Former Member
0 Kudos

Hi,

How to assign an internal activity to a WBS element?

Thanks!

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

actually in book "project management: SAP PS" SAP Press, it is written that - "In WBS scheduling, exactly those activities are scheduled that are assigned to these WBS elements. Therefore, you can schedule individual parts of a project without scheduling all activities of a network."

no here i don't understand that "without scheduling all activities of a network". does this mean that we can have a network spreaded over more than one wbs elements?

Thanks!

Former Member
0 Kudos

Yes.

Network has various activities.

These activities may be assigned to different WBS elements.

Thus one Network spread over various WBS elements.

SSanjay

Former Member
0 Kudos

Hi,

why WBS scheduling is used?

thanks!

Former Member
0 Kudos

In WBS scheduling start date is taken from WBS Basic dates for forward scheduling and end date in case of backward scheduling.

Former Member
0 Kudos

hi

check in the right hand side there will be a WBS Element field.