Hi, I need your help, i used SAP 4.6C, and i have problem to rescedule project with order already setup.
i used bottom up scenario for this project, and changed date in network header, why WBS date and order date not changed at all refer to new date in network header?
what should i do to changed automaticly?
best regard, thx
After changing the date in any activity in project, you have schedule the project again & save it.
Try this, it may solve your issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i mean that if i chaged date on Network, with bottom up scenario and service order setup,
but why the date in WBS not changed automat, so i must changed one by one. and date in servicer order not changed at all.
i need to shifting in new date on the project automat with all elemen in project. can i?
or i must changed semi automat?
After i tried, i realize now. a lot of step to changed date in Project and all wbs and order existence.
first, change date in network
second, used C29 to change WBS and order date
tird, used C20 to change start date of project
thx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have u rescheduled the project after changing the date in network header?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
have you run the transcation CJ29.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.