on 03-09-2009 5:08 PM
Good Day;
Does anyone know if CHaRM has the capabilities to migrate transports (within a maintenance cycle) to the same system multiple times?
Let me explain.
When we move a maintenance cycle (release) through our landscape we move from;
Development system - Quality system - Volume system. Then to production
UAT is being done in both the quality system and the volume system.
Once all testing is complete, we refresh the volume system with a fresh copy of the production system and re-import all the transports. This is to allow our BASIS team to do regression (batch) and load testing.
Is there a way to use CHaRM to migrate the transports or is this something that needs to be done manually (as it is today).
Thanks All,
Regards
Don Newton
Just Ceaning up
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.