on 03-09-2009 2:07 PM
Does SNP optimizer considers the forecast in the past as a requirement?
I tried with standard book and dataview but SNP optimizer did not consider past forecast. I checked optimizer log, forecast was not there also.
Am I missing something? Or is it default behaviour?
Thanks.
Hi
Yes that is the default behaviour, essentially the Optimiser has assumed that anything in the past has already occurred and will only start to plan demand from the first bucket onwards.
Regards
Ian