SAP STANDARD REPORT CJI5 - DISPLAY COMMITMENT LINE ITEMS FOR PROJECT

Former Member
0 Kudos

Hi Experts,

I would likt to konw something about the values being displayed in the report CJI5. After running this report I found 2 Columns - 1) Plan Valur RCrcy & 2) Value in rep.cur.

Can anybody explaing the meaning of the values appearing in the above mentioned 2 Columns.

In my case when I processed this report I found that value in both the columns are different. For example

1) Plan Valur RCrcy = INR 212,159,544

2) Value in rep.cur. = 80,773,428

I would also like to know why the above mentioned values are different & which value is to be considered as a COMMITMENT value/

Warm Regards

Ashok

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

In CJI5 ,

1) Plan Value Rcrcy is the Total Plan commitment.(PR & PO)

2)Value in rep.cur is the Balance commitment

i.e if your Plan Value Rcrcy.= 212,159,544 - (total plant commitment)

and Value in rep.cur. = 80,773,428 - (your Balance Commitment)

This means you have done actuals of (Plan Value Rcrcy - Value in rep.cur.)

i.e 212,159,544 - 80,773,428 = 131,386,116 INR.

which is booked through Goods Reciept and SES

Regards,

Nitin

Edited by: Nitin Ghadge on Mar 9, 2009 4:01 PM

virendra_pal
Active Contributor
0 Kudos

1) Plan Valur RCrcy = INR 212,159,544 - this is the totalpplanned commitment say P Req

2) Value in rep.cur. = 80,773,428 - this is the actual commitment say the amoutn in PO