Milestone invoicing......in cj20n

Former Member
0 Kudos

Dear Expertsu2026.

Milestoneu2026..Invoicing.

Created projectu2026wbsu2026networku2026Activities.

Created purchaser requ2026u2026with network activity.

Milestone attached to Activity/WBS(confuse)

Then I have to gou2026.editu2026.activityu2026invoiceplanu2026

Here how to copy milestone dates(confuse).

Then PReq will moves to PO.

Plz explain next processu2026u2026u2026u2026u2026u2026u2026u2026u2026u2026u2026u2026u2026u2026u2026it will be helpful to complete u2026

I have refered..

Regards

Chandra

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Next steps,

in the invoicing plan screen, click on dates for milestones- enter the N/w or WBS- u will get all the milestone in that N/w -


select the milestone u want to add as invoicing plan (enter % or the amount)--- go back & save.

u can also use reference for attaching invoicing plan in PO.

Regards,

Shruti.

Edited by: Shruti Meti on Mar 7, 2009 10:29 AM

Former Member
0 Kudos

Dear Shruti.........

Thanx for your reply.

but can u plz explain the invoicing plan screen (phase).

Tcode...and....process.

Regards

Chandra

Former Member
0 Kudos

Hi,

Select the activity which contains milestones(or for which u want to attach milestone)gou2026.editu2026.activityu2026invoiceplanu2026

here click on DATE FOR MILESTONES -


enter N/w which contains the activity(u want to attach the milestone) -


here u will get the list of milestones , select the milestones u want to attach.

Regards,

Shruti.

Former Member
0 Kudos

Hey...thanx....for continuous support.

Im clear what u said about the concept....i want to know..after PO...it will go to MIGo...MIRO...Payable account....where these milestone has to confirm in which phase.

Regards

Former Member
0 Kudos

Hi,

According to me Invoicing plan is mainly used for work orders where there is no GR.

so on the process of work completion the activity is confirmed(milestone based).

Eg: consider u have a work order with terms & conditions as

1) advance (20%)

2) payment after 1/2 of completion of work (50%)

3) payment after full completion of work ( 30%).

so u will confirm the activity with 20% & entering date in milestone confirmation(for advance).

simillarly for the other payments also.

for comfirming the activity- select the activity editactivityconfirm.

in the same process it will ask for milestone dates also.

once u confirm the activity % wise the Billing block for billing plan/invoice plan dates gets removed automatically nad u can invoice(MIRO).

Regards,

shruti.

Edited by: Shruti Meti on Mar 7, 2009 1:47 PM

Former Member
0 Kudos

Thats....good explaination.....

Thanx...Regards

Chandra