on 03-06-2009 10:10 AM
Dear PS experts,
Would appreciate if you could help me to identify which table should i use to capture/calculate project budget supplement, return and transfer.
Thanks in advance!
Best regards,
Eila
Or you can use only RPSCO which will give you totals value
Budget Type (VORGA)
= KBUD for original budget
=KBR0 for returns
= KBN0 for supplements
= KBFR for Releases
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Pass Objr of WBS to this tables
BPEG Budget revision header
BPEJ Budget revision header
BPGE Overall/annual budget
BPJA Overall/annual budget
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.