Tables for budget supplement,return and transfer

Former Member
0 Kudos

Dear PS experts,

Would appreciate if you could help me to identify which table should i use to capture/calculate project budget supplement, return and transfer.

Thanks in advance!

Best regards,

Eila

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Or you can use only RPSCO which will give you totals value

Budget Type (VORGA)

= KBUD for original budget

=KBR0 for returns

= KBN0 for supplements

= KBFR for Releases

Former Member
0 Kudos

Hi All PS experts,

Thank you very much!

This helps a lot..!

Regards,

Eila

nitin_patoliya
Active Contributor
0 Kudos

Pass Objr of WBS to this tables

BPEG Budget revision header

BPEJ Budget revision header

BPGE Overall/annual budget

BPJA Overall/annual budget

Regards