on 03-06-2009 9:07 AM
Hi to all
Is it possible to generate planned orders and further proceed to production order through projects WITHOUT MRP run?
Regards
surya
don't think so, but wait for others !!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
create the production order in CO01 and assign WBS element in the assignment tab of the order.
whether it ll solve ur purpose....
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you try transaction CO10 and check.
Regards,
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't think it's possible without MRP.
But why do you want to avoid MRP? Without MRP how do you do availability check?
In CO01 you can create Production order, but it may not have any reference to your project.
You have to use MRP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.