hi

in my scenerio work and duration in DAY. when im confirming work by entering processing% system will giving below error for the unit DAY

Only 0 decimal places are permitted for un

measure DAY

but i want the decimal place for the unit DAY in confirmation.

system not accepting decimal for unit DAY but accepting decimal place for unit H and Seconds

what can i do. Pls help

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

OPJO will help you. Select Time in dropdown first and then clcik "Unit of Measurement"