Unit of work

Former Member
0 Kudos

Hi ,

My requirement is that while creating internal activity in project once enters the work center name in work center field the activity type automatically comes from the work center. The same way I need the unit of work also should come based on the activity type unit.

Please help me resolve this issue.

Thanks

S.Murali

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

what KP told is absolutely true,

if u want, try with the exit CNEX0028 and function module EXIT_SAPLCOZR_001 and take the help of an abaper,

it may possible.

ashis

Edited by: ashis mohanty on Mar 6, 2009 11:08 AM

Former Member
0 Kudos

hi

Unit for work and duration will come from ur network profile parameters OPUU by default

Regards

KP..

Former Member
0 Kudos

Thanks for your reply,

But I want the unit of work from activity type. For example the activity type has unit hours I want the unit of work also the same unit hours.

Thanks

S.Murali