We're upgrading our ERP, and I need to know what I need to change in our PI/XI to link they to the new environment...

The IP's and hostnames will be the same, and the upgrade is only to apply the new version of SAP ECC 6.

I need to change something, or all my environment will work?!

Thank's

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Nothing is change!

Thank's

Former Member
0 Kudos

Hi,

As per my understanding it should work without any problems.

Regards,

Sarvesh

Former Member
0 Kudos

sorry..I didnt see the question properly

Edited by: Kumar on Mar 5, 2009 3:25 PM

Former Member
0 Kudos

Changes:

1.Partner profiles

2.RFC destinations

3.Business systems

4.Technical systems