I have a problem...

The user issues a material from MIGO_GI from plant to plant

Material: M

From Plant : P1

To Plant P2

Special Stock "Q"

Plant P1 WBS : WBS1

Project PR1 Plant P1 is assigned

Project PR2 Plant P2 is assigned .

when MIGO_GI 0r MB1B is done the plant P2 any WBS can be enetered the system is accepting the WBS and creating the WBS which is not existing in the Project P2.

Ideally the system should check whether the WBS is there in that Particular Plant and Project ?

Please Help.....

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Solution not found

Former Member
0 Kudos

hi

In standard SAP this functionality of validation is not there. you have to write your logic and activate the User Exit of goods movement.

Former Member
0 Kudos

But Ideally it should be apart of the standard functionality ?

If this is the case the system creates an WBS entry in the Other project wrongly which is Unjustified.