Dear SAP experts,
I have a problem...
The user issues a material from MIGO_GI from plant to plant
Material: M
From Plant : P1
To Plant P2
Special Stock "Q"
Plant P1 WBS : WBS1
Project PR1 Plant P1 is assigned
Project PR2 Plant P2 is assigned .
when MIGO_GI 0r MB1B is done the plant P2 any WBS can be enetered the system is accepting the WBS and creating the WBS which is not existing in the Project P2.
Ideally the system should check whether the WBS is there in that Particular Plant and Project ?
Please Help.....
Solution not found
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
In standard SAP this functionality of validation is not there. you have to write your logic and activate the User Exit of goods movement.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.