Net Price muyst be greater than Zero

Former Member
0 Kudos

While creating the contract I m getting error net price must be greater than zero. Can anybody suggest me the reason ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Anuradha,

the possible reason may be the gross price from the pricing schema may not be flowing.Please check the condition tab in PO & put the gross price manually. & save the PO. you wont get this error.

Amit

Former Member
0 Kudos

Hi Anuradha ,

This is because of price is not input in the contract ,You can resolve this error by following ways.

1.Maintain info record ME11 for material , vendor and plant combination and create a contract price should automaticaly come in contract.

2.Maintain condition record for material , Vendor and plant combination and create a contract price should automaticaly come in contract.

3.Enter the price in contract manualy.

Thanks

Niranjan

.