TECO status is erasing person assignement planning in network activities

Former Member
0 Kudos

Hello,

When i pass my project in TECO, the system is erasing my person assignement planning for every activities. I cannot find back my entries in the tables KBEZ and KBED.

Is there a way to configure the system so that he keeps these data up to date in the activities?

Thanks in advance,

Nathalie

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I think this is standard, as setting TECO erases all plan data and thus deletes person assignment.

Regards

Answers (0)