Transfer Posting with referance to reservation

atul_rajmane
Participant
0 Kudos

Dear All,

For some items I am making manual PO and getting material in Plant Stock.

I am attaching same item in project and creating reservation.

I want to do trasfer posting from plant stock to project stock using this reservation.

Let me know how I can do it??

Thanks and Regards,

Atul R. Rajmane

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Let us assume you have procured a material X Manually.

GR has been done and corresponding inventory has been updated in Plant Stock.

Use movement type 412 Q for transferring the plant stock to project stock.

As you said, you are creating reservation (for WBS element).

Agianst the reservation you can consume the same material which you have procured

Thanks

Prem

atul_rajmane
Participant
0 Kudos

Dear Prem,

Thanks for inputs.

I followed the steps as you said. Its working

Thanks and Regards,

Atul R. Rajmane