Availability Control - Error in triggering Warning Message

Former Member
0 Kudos

Hi Experts,

I am activating availability control for budget using Activation Type 1- Automatic activation. Set tolerance limit as 90 and using Action 1- Warning.

When i budget in CJ30 by copying 100 % planned cost, it gives a warning saying availability check and i save it as i felt it is a standard. SAP behaviour.

In project, when i confirm the activity till 100% actual cost posting i dont get any warning message at all. But i tried adding new activity and planned cost in the same project later. So when it exceeds even little more than 100 % budget value and i try to save it, that time the Warning message is triggering.

Please suggest a solution.

Regards,

Kabir

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Also, don't forget to run CJBN everytime you've done any changes on budget setting

Regards,

-K-

prabu_kaliappan
Participant
0 Kudos

HI,

When your availability control will be active???.When u save the budget or when u release the budget????

Regards

Prabu

Former Member
0 Kudos

Hi Prabu,

When i save the budget in CJ30 itself the availability control check and gives me warning message then i save it.

But i want this warning to be triggered after actual cost posting / confirmation of activities and during saving of project in CJ20N. It triggers Availability control Warning message only when actual cost exceeds 100 % whereas i want it to be done for 90 %.

Please advise.

Regards,

Kabir

Former Member
0 Kudos

1-check again ur tolerance limit,

make sure u have set action as "1" for warning at 90%

and u have set action as "3" for error message at 101%.

2- check the cost element u r using is not under exempt cost element.

3- chech any user status is restricting in activation the availability control.

ashis

Former Member
0 Kudos

Hi Ashis,

I have checked the following also,

1. I have used Action '1' for 90 % . I didnt use other actions 2 & 3 even.

2. Cost element that we are using is not under exempt cost element

3. I have not maintained any user status.

Couldn't understand why Warning is triggered after 100 %. It should trigger at 90 % itself

Please suggest.

Regards,

Kabir

Former Member
0 Kudos

In Budget Profile transaction OPS9

Please Tick the option Releases

and then check if it solves ur problem.

Regards,

Nitin

Former Member
0 Kudos

Hi Nitin,

I ticked on Releases indicator also in OPS9. It's not solving the issue

Following changes happend,

1. It's not triggering warning even when it exceeds 100 %. Earlier it was triggered.

2. No warning message when i save budget in CJ30. Earlier it was triggered

So i have now unticked again on the releases indicator. Same condition prevails.

Regards,

Kabir

Edited by: Kabir on Mar 5, 2009 1:19 PM

Former Member
0 Kudos

hi,

In this case AVAC will get active when you will release the budget in transaction CJ32.

try this and then check any error you are getting.

Regards,

Nitin

Former Member
0 Kudos

Hi Nitin,

Thank you for the reply.

I tried the following;

1. Did budgetting in CJ30, copied 100 % planned cost and saved it. Got warning message while saving.

2. Released 90% budget in CJ32.

3. Then confirmed activities in CJ20N and actual cost posted for project. Again, till 100 % no warning message is triggered. But when it crosses slightly 100 % of the actual cost, then warning message is triggering.

Please advise if the above process is correct. Issue remains.

Regards,

Kabir

Former Member
0 Kudos

In Define Tolerance limits,

Please do two settings as follows,

first for usage 90% take Activity as 1 (Warning)

second for usage 100% take activity as 3(Error Message).

check whether this works, also run CJBN.

Regards,

Nitin

Former Member
0 Kudos

Hi Nitin,

I did as you said above. Its triggering the error message when the actual cost exceeds 100 %. It's working fine though i didnt try for this action 3 earlier.

But i dont understand why its not triggering action 1, warning at 90 % or more. Anymore suggestions please.

@Kealin - Thanks for the reply.

Thank you,

Kabir

former_member203108
Active Contributor
0 Kudos

What is the warning message you get when u save ur budget?

Former Member
0 Kudos

Hi Rifaee,

Following is the warning message i get during budget saving in CJ30. I copied 100 % of planned cost for budget.

*Budget Checks / Availability Control

Warnings were detected

Do you want to save your entries?*

To all others: Warning message, action 1 is not getting triggered above 90%. But error message,action 3 triggers above 100 %. Issue remains. Any clues please?

Regards,

Kabir

Former Member
0 Kudos

CLOSING THE THREAD.

prabu_kaliappan
Participant
0 Kudos

HI,

When your availability control will be active???.When u save the budget or when u release the budget????

Regards

Prabu

Former Member
0 Kudos

Hi

Kindly check for which activity groups you had activated.

Thanks

Prem

Former Member
0 Kudos

Hi Prem,

I have activated it for '++' all activity groups.