Dear All,
While creating inspection plan , in operation tab , which control key should I assign , if I want to check the material thru PO----GRN.?
Regards,
Hi Rohit,
If it is a simple inspection plan for a PO-> GR scenario, create an insp plan with usage 5 in the header and in the operation use std control key QM01 which has insp char required setting by default. For the
slected operation assign ur required MIC with IM and samp proc.
Regards
Venugopal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rohit,
Ensure Inspection characteristics required indicator is configured in the details of Control key.
All the standard control keys with QM* are applicable for the same.
Regards,
Keerthi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use Control key as QM01 , which defines inspection char Requirement.
Regards,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.