While creating inspection plan , in operation tab , which control key should I assign , if I want to check the material thru PO----GRN.?

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Rohit,

If it is a simple inspection plan for a PO-> GR scenario, create an insp plan with usage 5 in the header and in the operation use std control key QM01 which has insp char required setting by default. For the

slected operation assign ur required MIC with IM and samp proc.

Regards

Venugopal

Answers (2)

Answers (2)

former_member204463
Active Contributor
0 Kudos

Hi Rohit,

Ensure Inspection characteristics required indicator is configured in the details of Control key.

All the standard control keys with QM* are applicable for the same.

Regards,

Keerthi.

Former Member
0 Kudos

Hi,

Use Control key as QM01 , which defines inspection char Requirement.