Dear Experts..........

This is user req:

Im trying since long time plz express your views.

For example:

We got one order....construction.

now req is ...two orders have to control by one project.

x.1,x,2,x.3,x.4........these are first building wbs

Y.1,Y.2,Y.3,Y.4.....These are second building wbs.

Both x and y wbs are in same project....whenw e release the project both X and Y will relaese automatically.

i stheir any procedure to control only X wbs should relaese.

Y wbs should release after completing X wbs work.

Regards

Chandra

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

Your scenario is ont quite clear to us.

REL is status is pass on status for the lower level WBS. IF your X & Y are level 1 & LEve 2 WBS than in that case you should REL level 2 WBS.

If both X & Y are same level than you can control the same via user status.

Regards

Nitin

Former Member
0 Kudos

Thanx for your replies....

Venkat..........Ashish..........Nitin.

I have suggested release each WBS.

If both X & Y are same level than you can control the same via user status.....

Can i have some inputs

nitin_patoliya
Active Contributor
0 Kudos

If both X & Y are same level than you can control the same via user status

By this I mean to say that you can assign the status profile to repective WBS ELement X or Y and control the Release status. If you req. details step let me know your requirement in detail.

Regards

Nitin

Former Member
0 Kudos

Dear....Nitin,

Thanx for continuous support.............

Actually...this scenario is.....In one project....X1,x2,x3..and ..y1,y2,y3, wbs are in same level.

X...Wbs will construct one Substation.

After completing X substation we should start Y Substation.

I have planned to make two projects for...X.Substation..and Y.Substation

But now im thinking to release each WBS.mainatining (x and y )in single project

They want to show in single project...X and Y?

I have doubts......

After completing X work (X1,X2,X3,X4 WBS CAN I CLOSE these wbs only)Y should be active.

Or u plz provide some inputs dear.....with userstatus

nitin_patoliya
Active Contributor
0 Kudos

QThey want to show in single project...X and Y?

AYes you can map the same in Single Project.

QAfter completing X work (X1,X2,X3,X4 WBS CAN I CLOSE these wbs only)Y should be active.

Or u plz provide some inputs dear.....with userstatus

A If both are at same level than this is standard funcatioality...You can set Closed X WBS & after that Y can be in REL status. If I say in simple word than if WBS are on same level your can activate any type of status on it. It will not affect the other WBS.

I think your requirment is straight forward & can be achieve without user status.

Userstatus comes in picture when you wanted to control status change rights to perticular uesr groups etc. ...

Regards

Nitin

Former Member
0 Kudos

Yes.....actually i was seeing in wrong view this scenario.

Now im clear.

Thanx Nitin.

Answers (2)

Answers (2)

Former Member
0 Kudos

either user status or do nt release at project definition level, release individual wbs elements.

ashis

Former Member
0 Kudos

Using User status u can always control the release of the WBS.

Suggest to release each WBS to have control.

Is Y WBS create below the X WBS element?