on 03-04-2009 8:38 AM
I have activated the data source in lbwe.
Hi Sahana,
Have you enhanced the standard datasource 2LIS_13_VDKON?.
what we normally do for LO extractors is as follows.
1. Stop the MCEX Jobs
2. Delete the setup tables
3. clear extraction Queue (LBWQ)
4. Run the deltas for datasource 2LIS_13_VDKON to BW untill you get 0 (zero) records in BW
5. Transport the datasource.
6. Once the step 5 is succesfull tne restart the MCEX Jobs.
Regards
BN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have activated the data source in lbwe and tested in the r/3 dev.
We would like to move to quality. Do weneed to delete the set up table (as 2lis_13_vditm is available)
in quality and then move the tpt request or to run the set up table again without deleting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.