cancel
Showing results for 
Search instead for 
Did you mean: 

SAP-PS(activity element)

Former Member
0 Kudos

If we have more than 1 work center for an activity , we can assign thru activity element. But if we want to see the plan cost in the main activity(Of all activity ELEMENTS) or PLAN COST SHOULD BE SUMMARIZATION of main activity plan cost + plan cost of all activity elements , is it possible ?

Regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

if u plan activity by work center and activity and duration, its plan cost will appear for that activity only.

if u create further activity elements, then the plan cost will appear for those activit elements only, that planned cost will not be summarized for the parent activity.

ashis

Former Member
0 Kudos

hi

if you maintain the workcenter / Cost center and activity type price the cost will appear as planned cost in the activity (even if you use actiity element).

Former Member
0 Kudos

Respected Sir,

No , it's not like that in my case. Main activity plan cost is shown seperately while activity element under it is showing itsplan cost seperately. I want to suumarise total plan cost in main activity.

Regards,

Former Member
0 Kudos

if u r breaking ur main activity into activity elements, then there is no meaning of using work center,activity in the main activity rather it sud b in activity elements.

Activity elements will only takes the start/finish date of the main activity.

if u want total cost, u can see in the hierarchy report under the WBS element.

but for ur scenario, check any user exit available to address this, which will overwrite the total plan of activity elements into activity.

ashis