SAP-PS(Actual & plan cost)

Former Member
0 Kudos

1)When i am calculating my plan cost for an activity whose duration is 10days , working is 8h/day and rate is 50/hr , my plan cost is coming rs. 8000 instead of 4000. can anyone help?

After confirming an activity 100% , actual cost is not coming. Is there any customisation in confirmation or at any other place?

Regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear ashis,

activity price pln. is in hrs , work is in hours , exe. factor is blank.

problem still persists.

Regards,

Former Member
0 Kudos

Hi

Check the individual capacities maintained in workcenter. Check the capacity detailed tab. If you have maintained 2 individual capacities then the effective operating time will be 16Hrs.

Regards

Former Member
0 Kudos

Dear Hemant Sir ,

As I am new to SAP-PS , so after applying your solution also , I am not getting the desired results. So I am giving complete details of work centers and activity types defined by me as problem lies here only.

Work center :-

Basic data tab

Standard value key = sap0

Default value :-

Control key=ps01

Capacities tab :-

Other formula =sap004

Scheduling tab :-

Other formula=sap004

Costing tab :-

Co area =

Cost center=

Acttypeint pro =

=sap008

In capacity tab :-

Start=8.00

Finish=17.00

Break-1.00

Uti=100

Cap=1

Activity type (kl01) :-

Unit=h

Cat=*

Atypcat=1

Cost element=

Kp26 :-

Plan dis dis u p p p pl

8 2 2 h 50 50 00001 1

Where is the mistake ?

Regards,

Former Member
0 Kudos

normally plan cost of any activity = activity price maintained in KP26 X work duration in general data

Activity price planning and ur work should b in same unit.

Pls convert the unit into either hour or day.

second thing, if u have used any execution factor, ur plan value may get increased,so check that also

ashis