Error cProject 4.0 after update

Hi experts,

We have updated cProject 4.0 from SP8 to SP13 (CPRXRPM for ABAP and BPPPMDC for Java).

Now we have this error when we try to launch cProject :

The following error text was processed in the system EC6 : Syntax error in program /1BCWDY/YXA35AAEJAF59288U1RW==CP . 
The error occurred on the application server SERVER_EC6_00 and in the work process 0 . 
The termination type was: RABAX_STATE 
The ABAP call stack was: 
Method: CONSTRUCTOR of program CL_WDR_CLIENT_COMPONENT=======CP
Method: IF_WDR_COMPONENT_FACTORY~CREATE_COMPONENT of program CL_WDR_CLIENT_COMPONENT=======CP
Method: IF_WD_COMPONENT_USAGE~CREATE_COMPONENT of program CL_WDR_COMPONENT_USAGE========CP
Method: CREATE_UNINITIALIZED_VIEW of program CL_WDR_VIEW_MANAGER===========CP
Method: GET_VIEW of program CL_WDR_VIEW_MANAGER===========CP
Method: BIND of program CL_WDR_VIEW_MANAGER===========CP
Method: IF_WDR_VIEW_MANAGER~MAKE_VISIBLE of program CL_WDR_VIEW_MANAGER===========CP
Method: PERFORM_NAVIGATION of program CL_WDR_CLIENT_APPLICATION=====CP
Method: NAVIGATE of program CL_WDR_CLIENT_APPLICATION=====CP
Method: DO_NAVIGATION of program CL_WDR_WINDOW_PHASE_MODEL=====CP

AS Java is SP9, do we have to update it ? if yes, which SP ?

Thanks in advance,

Mik.

Former Member
replied

Hi,

SAP Note 1171775 should fix the issue.

Kind regards,

Florian