on 03-02-2009 1:58 PM
hi
i just want to know how the cost is calculated in work center and how to define a work center for a project
is there any formula that has to set in work center? and plz give an example
subhro
HI
THANX FOR UR ANSWERS
SUBHRO
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
SAP004 => the duration (important for scheduling)
SAP08 => the capacity (important for capacity requirement and costs. )
Example, an activity takes 10 hours, need capacity 40 hours, becasue there are 4 persons work at this activity on the same time.
And donot forget to maitain the cost center of the workcenter tab 'costing' .
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Before u create a work center by Tcode CNR1, a cost center and activity type has to be created.
1. Create cost center - Tcode KS01
2. Create Activity Type - Tcode KL01
3. Then goto Tcode KP26 and input price for that activity type related to that cost center for a defined period.
Then create workcenter by Tcode CNR1. In Scheduling tab use Formula, SAP004. And in Costing Tab use formula, SAP008.
This is the way to create a work center and cost will be calculated based on the price you have given in KP26.
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.