on 03-02-2009 1:38 PM
Hello All,
In CO09 transcation, if i enter a materail number that contains a lot of components, does it check the ATP of those componenets also before giving an avaliable date for that materail?
Regards
Hi,
It checks for the final material availability, when a final material is ready all its components qty will be reduced.
When a final material is not available then based on the settings when it is available it give the result for final material, it will not check for component materials individually.
Regards
Sree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi there,
This depends on the item catg setup. Item catg is proposed based on
Sales doc type / item catg grp / usage.
If the item catg grp is LUMF, then the system will confirm the main item if all the child items are confirmed.
If the item catg grp is ERLA, then the system will confirm the main level item even if the child level items are not confirmed.
Regards,
Sivanand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.