You can refer this link for the logic being used behind the statistical postings. You can use statistical Project whenever Profit cneter accounting is used. Virendra has suggested cases..
http://help.sap.com/saphelp_470/helpdata/en/08/5142c343b511d182b30000e829fbfe/frameset.htm
you can refer the case 1 as above suggested in details
http://help.sap.com/saphelp_470/helpdata/en/2a/f9f383493111d182b70000e829fbfe/frameset.htm
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Case 1
you can use IM budgets to monitor costs of direct procurement of assets by using statistical projects
Case 2
If you PS/ PM integration or internal orders then you can budget for the PM orders using statistical projects
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chandra,
If you want to monitor the cost of particular event or Work which is treated as a project in a Hierarchical way or in different heads and this cost is no where related to WIP Value or no more further settlement to receivers like Asset under Constructioin, GL Account like that.
In this scenario WBS Element is treated as a Statistical Element and system requires a Cost Center for Capturing the actual Cost. you can monitor the statistical cost in report just for information purpose.
Regards,
Hari Krishna.K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.