on 02-27-2009 8:02 PM
I have an escenario where the client needs another option to calculate the material plan costs, but need to identify the correct user exit.
In transaction OKYF exist the option "U Valuation Price with User Exit" but need the user exit to use.
Hope to receive information soon...
Best Regards...
Check these:
COPCP002
COPCP005
WBWE0001
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the information, COPCP005 solves the issue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I allready have the config for unit costing for material on the network, but this checks the price on the last purchase document.
The client want's to use the value registered on the info registry without checking the purchase document..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
you can use unit costing for material option for this...
Automatic netowrk costing for material component
you need to maintain proper costing variant for material component in config.
in projects assign material then select material -edit - cost - unit costing.
which will get reflected in network cost in CJ40.
Venkatesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.