Dear Experts,

If we want to issue goods for a particular project via a different project stock, what would be the ideal process flow?

Appreciate your guidance on this.

Thanks in Advance,

Dileepa.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Before the movement type 415 - Q in MB1B u put staus as technically complete for the WBS from where u want to remove stock as stock is transfer from WBS A to WBS B the actual cost will also get tranferred from A to B. Due which the budget allocated for WBS A can be used for genrating Purchase commitments. To avoid this u shuld do TECO before stock transfer. After which u can return the budget from WBS A.

Rgds

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In addition to Hemant's reply, the suggested movement type will transfer stock from other project to required project. You need to further issue material from this project stock to network activity using MB1A.

Regards

Former Member
0 Kudos

Hi

Try MB1B via movement type 415 Q.