on 02-26-2009 12:04 PM
Hi all,
I have a Small Problem ,When i m running T Code CJBV for the activation of Availability Control it is not working but if i run CJBN (Reconstruct) then It gets activated.
1. Can anyone suggest wat could be the problem.
2. Is it problem if i run CJBN everytime,if yes then wat?
Your early reply will be appreciated.
Regards
Shashi
Hi
Please see below SAP recommendation on the subject.
I think this addresses your problem.
Reconstruct Availability Control
In this IMG activity, you reconstruct all the data for availability control. The assigned values are recalculated and references are created to the objects that have budget.
The new budget profile settings are copied into the budget table.
Recommendation
SAP recommends that you reconstruct the PS Info Database with transaction CJEN before activating availability control
Activities
Carry out this step if:
1. you install a new release
2. you haved changed the availability control settings in the budget profile (e.g. from overall to annual values)
3. you have changes the tolerance limits for availability control
4. you have defined exempt cost elements - that is, cost elements which are not subject to availability control
5. you have changed the order update settings for orders for projects
6. you suspect errors in the data - for example, in objects from older releases or after incorporating corrections relating to budgeting or availability control
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As I see from the mail postings, looks like you have carried a roll out for another company code. Since these Budget postings are dynamic, I suggest that you follow the SAP recommendation in this regard.
Once you bring the whole process on line, you may not face any problems with new projects.
Venu
Hi,
In your budget profile (OPS9), under Availability control set 'Activation Type' to 1. This will ensure that AVAC gets set after budget entry. For existing project you will have to run CJBN, new projects will set AVAC after budget entry.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.