Commitment reset from PO using Final Invoice indicator

Former Member
0 Kudos

Hi guys,

I have an issue here.

I have PO which is linked to a WBS. The PO quantity is one. I have a GR and IR for One quantity. There is a credit memo IR for -0.7 items. When i set the final invoice indicator in the PO the Commitment in the PO is not getting reset and I am not able to close the WBS. Please let me know what might be the issue.

regards,

MP

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Please see if the SAP note 733733 looks relavant.