Dear SAP Gurus,

i have a question regarding DO creation,,,i cannot create DO because of this message

no schedules lines for this item,,,

how to correct?

thank you very much

Former Member
Former Member replied

In VA02, choose the item > go to schedule line of theitem > click on the "Shipping " tab below.

Here you will find the Material availability date ,Transportation Plnning date,loading date etc.

Note down the material av date & tr.planning date.

Now, in create delivery (VL01N), enter your Shipping point, in the "Selection date" field enter the Mat. availability date or Tr.planning date whichever is earlier and proceed.