on 02-26-2009 7:12 AM
hi all
While creating shippment cost i got error Shipment 89547495 has overall status 1. Shipment cost type 0001, however, requires overall status 5.I have changed the status but it still gives same error.Second thing can i directly go to do PGI to see the truck load status as my purpose is to check the saes order quantity with the capacity of truck.Suggest mw how to get this stage.
cheers
shalsa007........
Dear,
Since shippment document status is 1 it means Planning completed only, if you want to create a shippment cost shipment document status should be as shippment end ie 7.
for this you need to click all the dates in shippment documents as follws.
Planning
Check-in
Loading start
Loading end
Shpmt completion
Shipment start
Shipment end
if document status is 7 - Shipment end then you can create shippment cost document.
Hope it helps
Regards
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
any suggestions..............
cheers
shalsa007.............
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.