on 02-26-2009 12:02 AM
Hi,
The requirement is that you have a server reapir needed and you are not sure about the amount of labor and also amount for any spares?
So I need to create a SC and release against a Contract, for example I have a contract with IBM for their servers with both Service lines and Spares lines.
I could think of creating a limit item SC, say for $1000 and released against this contract with IBM. And it created a PO in ECC with Item Category D
Then, the work is performed and I tried to create a confirmation in SRM with line one with Serice and Labor for $300 and line two with spare parts of $700.
But I couldn't confirm against any material line as the PO is purely Service.
So, my question in general is, I am pretty sure many big companies might have faced this scenario in procurement of unknown amount of goods and services on one PO/SC.
What is the easier/other option to do this.
I know that we can't create two limit item PO's and more over, one line should be for materials.
Please share your input on this.
Thanks,
CS
Hi Chinna,
I have not extensively worked with services but my suggestions
Assumed that you created a Limit SC with the option of confirmation.
Thats why you have refered a r/3 Contract in limit sc of contract TAB.
Hope that you have created a PO in R/3 for the services.
so can you create a service entry sheet in r/3 rather than SRM . it is a workaround
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Muthu,
Thanks for the response, I respect your work in sdn, you almost have solutions for most of the questions, anyways, I for got to mention that we are using ECS. The copy of PO created in ECC is services PO, the contract/PO is all in SRM.
My challenge is to crate scope of unknown labor and materials in one SC/PO.
Thanks,
CS
Hi CS,
plz refer these ..following notes and links. it is a limitations of limit PO.
Note 1302125 - Not able to add two or more limit items in purchase order
Note 1054487 - Multiple limit items allowed in purchase order
Note 1243836 - Manual entry of invalid contract allowed in contract limit
Note 1301483 - PO with two or more limit items goes to Error in Process
coming to your point unknown /always it is necessary to mention a price in PO .it is a rule.it can not be flexible.
regards
Muthu