In VA01, when I try to enter a plant, system pop up an error: <Material Number XX> is not defined for sales from <Country YY>

The document type is OR.

Item Cat. is TAN.

In OVK1 and OVK4, the relevant tax country and tax category are already defined.

Any advise would be appreciated.

VT

Accepted Solutions (1)

Accepted Solutions (1)

former_member550050
Active Contributor
0 Kudos

Dear Friend

Plant will come automatically in VA01 either from CMIR,or CMR or MMR

why are you inputting plant manually in VA01?

This is my first qn?

If you are changing plant which is which has been automatically determined by the system then check your OVX6 settings

that is in enterprise structure--assignment-SD---Assign plant to sales org and distribution channel

Something must be missing in your enterprise structure settings only

As the other friend said also check VOR1 and also VOR2 (for a safety sake only but i dont think these t codes has got something to do with your error)

Hope this will solve your issue

Regards

Raja

Answers (5)

Answers (5)

Former Member
0 Kudos

It seems like the material was created wrongly,

now it works when I create a new one.

Thank you.

Former Member
0 Kudos

Hi Vitthavat,

Check the country maintained for the plant for which the meterial is created.

Thanks,

Swamy H P

Former Member
0 Kudos

Hi u have to assigh material to sales area in master data

Former Member
0 Kudos

Hi,

Goto Material Master Data change for that particular material using in sales order give the Division in Basic Data 1 View or Sales View.(T code MM02)

Former Member
0 Kudos

Hi,

Make common dis chanels, and common division in IMG sd, master data

regards,

sadanandam kasarla