Day to Hour conversion

Former Member
0 Kudos

where is the setting by whch number of hours for unit DAY can be 8hours/12 hours or 24 hours, as per the desired settings.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In standard SAP 1 day = 24 hrs.

It depends upon the workcenter, you use how many are working hrs in a day.

In CR02, goto capacity tab of workcenter and double click on capacity, you can chnage working hrs here.

Regards